Overview & Objectives

McCormick, the global leader in flavour, enlisted our team to deliver a bespoke internal envelope solution at their new facility. The scope of works involved constructing a large-scale temperature-controlled environment within a steel-framed industrial unit, requiring expert design coordination, precise panel installation, and careful integration of services.

Scope of Work

This project centred on the supply and installation of a full hygienic panel envelope to form a large internal food-grade space. The works included:

  • Lifting and installation of 100mm PIR insulated composite panels to full height walls
  • Creation of integrated service openings and access doorways
  • Detailing for future integration of refrigeration systems and ventilation ducts
  • Design and placement of ceiling panels, supported from galvanised steel purlins
  • Panel cutting and notching around complex steel framework with no tolerance for error

Given the height of the internal walls and ceiling span, works were completed using powered access (scissor lifts and forklifts with vacuum panel lifters) to ensure safe and efficient handling of materials. Installation of the ceiling was carefully sequenced to accommodate early-stage M&E installation while keeping the project on programme.


Challenges & Solutions

The key challenge was the need for extreme precision during the build. The wall panels interfaced directly with the steel structure, and the tolerances required close coordination with structural drawings and live measurements on site.

To manage this, our site team used laser measurement equipment and worked closely with the client’s main contractor to ensure full alignment with the steel portal frame and building services strategy. Bespoke flashing and panel cuts were fabricated and installed in sequence to maintain airtightness and hygiene standards.

We also phased the build to enable partial handover of the space to follow-on trades, while maintaining safety and cleanliness across the live construction zone.